    A key to Biden’s lagging wind energy goal will set sail after the election


    Wind turbines, solar panels and a coal-fired power station in China.

    Owngarden | Moment | Getty Images

    The United States is producing less than 1% of the wind power it wants to generate by 2030. But an enormous boat promising to change that is about 89% built, and when it’s done next year, the real race to catch up begins.

    The ship, named the Charybdis after a mythological Greek sea monster, won’t set sail until next year, potentially after one of the most pro-green energy administrations in history has left the White House. And as Eric Hines, the director of Tufts University’s offshore wind energy graduate program, puts it, “We’re going to need somewhere on the order of five of these installation vessels in just a few years.”

    The Biden administration wants the U.S. to generate 30,000 megawatts from wind power within the next five and a half years. As of last year, that figure stood at just 42 megawatts, putting the nation far behind Europe — which added 18,300 megawatts of new wind energy capacity in 2023 alone, according to WindEurope.

    In recent years, constructing massive offshore windmills has come with headwinds from supply chain snags to higher interest rates. But the U.S. faces an added logistical puzzle from a 100-year-old maritime law that, along with those other factors, has contributed to project delays and even cancellations.

    The outcome of November’s election isn’t likely to affect the Charybdis, whose operator plans to take advantage of green energy tax credits in the Inflation Reduction Act. But the prospect of a new administration much less keen on renewables could hamper additional projects.

    Republican presidential candidate Donald Trump claimed at a New Jersey rally in May that offshore wind installations harm whales, saying, “We are going to make sure that ends on day one. I am going to write it out in an executive order.” (“There are no known links between large whale deaths and ongoing offshore wind activities,” the National Oceanic and Atmospheric Administration has said.)

    The first major parts of the boat were laid down in 2020, kicking off a $625 million project between Dominion Energy and Seatrium AmFELS, which is building the massive vessel in its Brownsville, Texas, shipyard. At over 30,000 tons and with 58,000 square feet of deck space, the Charybdis will be able to transport 12 blades at a time, each measuring 357 feet and weighing 60 tons.

    We’re going to need somewhere on the order of five of these installation vessels in just a few years.

    Eric Hines

    Tufts University Professor

    Just as important as its technical specs, the boat will also be able to meet the requirements of the Jones Act, a 1920 merchant marine law that says cargo shipped from one point to another within the U.S. must be carried by an American vessel. And so far, there’s no American vessel capable of carrying wind turbine parts directly from shore to installation sites miles off the coast.

    The Charybdis’ first project will be Dominion’s offshore wind farm under development 24 miles east of Virginia Beach. Once completed, its 176 turbines are expected to deliver 2,600 megawatts of energy, enough to power over 900,000 homes. But to install its first two pilot turbines, it had to stage the parts in Canada to comply with the Jones Act, adding long travel times and related costs.

    “Obviously, you don’t want to install a large project like that,” said Mark Mitchell, the Dominion Energy senior vice president overseeing the Coastal Virginia Offshore Wind project — which, at $9.8 billion, is currently the largest and priciest in the country.

    Instead, the Charybdis will be able to pick up components on the coast, sail out to the wind farm site, and plant itself into the ocean floor using four 30-story legs that will transform the ship into a construction platform. Then, using a crane with a boom longer than 20 full-sized vehicles lined up bumper to bumper, it will begin assembling the turbines.

    After completing the Virginia project, the ship will be available for contract to other offshore wind projects along the nation’s coastline. Mitchell hopes the Charybdis can do more than complete wind farms already in the works, but inspire developers and planners to propose new ones too.

    “It’s a little bit of the chicken or the egg. As we start committing the projects, others can commit to infrastructure like this,” Mitchell said, adding that state and federal incentives will “pass right down to our customers.”

    But in other cases, federal subsidies have not been enough to overcome rising costs. One major reason: the Federal Reserve, which raised interest rates 11 times between March 2022 and July 2023, the fastest pace it has raised rates since the early 1980s.

    It’s a little bit of the chicken or the egg. As we start committing the projects, others can commit to infrastructure like this.

    Mark Mitchell

    Dominion Energy

    Higher interest rates make it more expensive to finance large construction projects like wind farms.

    “The cost of construction is very high,” Hines said. “If you imagine the time while one is constructing a project, you’re not making any money off the project. And so money that you borrow that time to construct the project, there’s a premium on that money, and the lower the interest rates, the better.”

    Last year, Danish company Orsted canceled two projects off the coast of New Jersey, citing “challenging” conditions.

    “Macroeconomic factors have changed dramatically over a short period of time, with high inflation, rising interest rates, and supply chain bottlenecks impacting our long-term capital investments,” Orsted said in October. The company paid the state $125 million to cease development.

    The Biden administration acknowledges the pressure from higher interest rates and points to tax credits in the IRA as a way to offset them.

    “We know that there are a number of different tools that will help us overcome some of those macroeconomic challenges,” said Jeff Marootian, principal deputy assistant secretary for the Office of Energy Efficiency and Renewable Energy.

    He acknowledged that the Biden administration’s goal of 30,000 megawatts of wind energy is “ambitious” but pointed to projects in the pipeline as a sign of things to come. The Energy Department has tallied nearly $6 billion of investments to develop offshore wind over the last few years, including in 17 manufacturing sites and at 15 ports.

    “Those are the kinds of investments that we need to continue to see in order to reach the president’s goals,” Marootian said.

    https://image.cnbcfm.com/api/v1/image/107322808-1698231177923-gettyimages-1415259307-img_1265.jpeg?v=1698231314&w=1920&h=1080



    Source link

    Latest articles

    spot_imgspot_img

    Related articles

    Leave a reply

    Please enter your comment!
    Please enter your name here

    spot_imgspot_img