- EPA removes generator exemptions, forcing hyperscalers to follow strict federal air rules
- Portable turbines used by xAI now need full permits before operation
- AI data centers face delays as grid alternatives require federal approvals
The US Environmental Protection Agency has introduced a rule that removes exemptions for gas turbine generators, closing a loophole which allowed the rapid deployment of temporary power systems.
The change affects hyperscalers which rely on portable turbines to supply electricity before their sites received full grid connections.
Going forward, companies that previously benefited from local ordinances can no longer bypass federal requirements, meaning all gas turbines, regardless of duration or size, now require air permits under the Clean Air Act.
Federal oversight replaces local loopholes
The rush to power AI data centers has created unprecedented electricity demand, as sites housing millions of GPUs strain the US grid, forcing operators to adopt on-site generators to maintain operations.
Other hyperscalers have adopted similar measures, with OpenAI reportedly planning to use gas turbines at its first Stargate facility.
These turbines, often derived from cast-off jet engines, provide temporary relief while operators await full grid service, but will now be subject to the same federal oversight as permanent installations.
Elon Musk’s xAI startup relied on a county loophole to expedite the launch of a large AI data center in Memphis.
By using portable turbines, xAI reportedly powered a site with 100,000 Nvidia H200 GPUs within 19 days, a process Nvidia CEO Jensen Huang says normally takes four years.
The loophole allowed turbines to operate without a permit for up to 364 days if operators relocated them within that period, but local legal challenges from residents revealed environmental concerns and prompted scrutiny from federal regulators.
The new EPA rule does not ban portable or permanent turbines, but it increases the regulatory burden, as any company wishing to deploy these generators must now comply with federal air quality standards and obtain the appropriate permits.
The decision signals that reliance on temporary solutions to bypass grid limitations is no longer viable without federal approval.
Companies must now plan for extended timelines, potential environmental reviews, and additional compliance costs before bringing new sites online.
For operators racing to bring AI infrastructure online, the ruling complicates expansion plans.
Portable turbines, once a fast workaround, now require careful documentation, monitoring, and reporting to meet EPA requirements.
The impact on daily operations may vary, but the rule establishes that federal environmental standards take precedence over local ordinances.
Via Tom’s Hardware
Follow TechRadar on Google News and add us as a preferred source to get our expert news, reviews, and opinion in your feeds. Make sure to click the Follow button!
And of course you can also follow TechRadar on TikTok for news, reviews, unboxings in video form, and get regular updates from us on WhatsApp too.
https://cdn.mos.cms.futurecdn.net/fkx6mFKRAjjR8ponn66BT3-2560-80.jpg
Source link